Pre-generated exampleConstruction General Permit

Sample completeness report — Hickory Ridge — Phase II Subdivision

A representative CGP application package: NOI, SWPPP, and site map. This report was pre-generated from a realistic three-document submittal showing the full range of findings the system produces — complete, needs review, and missing/deficient. For a live analysis with your own files, visit the Analyze page .

Construction General PermitTNR100000HIGH classification confidence

Hickory Ridge — Phase II Subdivision

Applicant: Hickory Ridge Developers, LLCLocation: Murfreesboro, Rutherford County, TN (35.7621°, -86.3214°)Analyzed 2/14/2026, 3:43:22 PM
69% complete
Overall completeness
Substantial deficiencies
0 requirements checked
0
57%
Complete
0
29%
Needs Review
0
14%
Missing / Deficient
CGP NOI (CN-0940)
noi-form.pdf
4 pages · 172.1 KB
DOCUMENT PREVIEW · CGP NOI (CN-0940)
noi-form.pdf

Sample NOI form — CN-0940 (Rev. 11-21). In a live session, the actual uploaded document is rendered here. Clicking a finding scrolls to the relevant page.

p. 1
p. 2
p. 3
p. 4

Cross-Document Validation

4 checks
  • Site acreage consistency
    noi-form.pdfswppp.pdfsite-map.pdf

    NOI states 4.2 ac total disturbed; SWPPP §1 states 4.5 ac; site map measurement ≈ 4.3 ac. Reconcile before issuance.

  • Outfall coordinates match
    noi-form.pdfsite-map.pdf

    OF-001 and OF-002 coordinates on NOI page 2 match site map labels within 0.0001° tolerance.

  • Signatory identity consistent
    noi-form.pdf

    Marcus Whitfield, Managing Member, listed on both NOI signature block and CN-1090 contact form.

  • SWPPP engineer license on file
    swppp.pdf

    SWPPP signed by James Lin, TN P.E. #28391; verified active per TN BAEE roster.

Findings

Notice of Intent (NOI) form completed and signed

HIGH confidenceCRITICAL

CN-0940 NOI completed in full. Operator: 'Hickory Ridge Developers, LLC'. Responsible official signature dated 2026-02-14 on page 4.

CGP §2; Rule 0400-40-05-.05(4)noi-form.pdf· p. 4

NOI submitted at least 30 days before land disturbance begins

HIGH confidenceCRITICAL

Estimated start date listed as 2026-03-10. NOI submission date is 2026-02-14 (24 days before start) — falls short of the 30-day minimum by 6 days.

CGP §2.2noi-form.pdf· p. 2

Public notice published in newspaper of general circulation

HIGH confidenceCRITICAL

No publication date supplied on NOI page 4. Field 'Date public notice published' is blank.

Rule 0400-40-05-.06noi-form.pdf· p. 4

Signed by qualifying responsible official

HIGH confidenceCRITICAL

Signed by Marcus Whitfield, listed as 'Managing Member' of Hickory Ridge Developers, LLC — a qualifying responsible official for an LLC.

Rule 0400-40-05-.05(4)noi-form.pdf· p. 4

Project location given in decimal degrees within the project area

HIGH confidenceMAJOR

Latitude 35.7621, Longitude -86.3214 entered in decimal degrees. Coordinate falls within the project boundary shown on site-map.pdf.

CGP §2.1.bnoi-form.pdf· p. 1

Total project area and total disturbed acreage reported

MEDIUM confidenceMAJOR

NOI lists 4.2 acres total disturbed area. SWPPP §1 narrative states 4.5 acres. Site map shows a disturbance footprint that measures approximately 4.3 acres. Values are within rounding tolerance but inconsistent.

CGP §2.1.dnoi-form.pdf· p. 1

Receiving water and 12-digit HUC identified

HIGH confidenceMAJOR

Receiving water identified as 'Stones River tributary, unnamed'. 12-digit HUC: 051301070304.

CGP §2.1.enoi-form.pdf· p. 2

303(d) impairment, ETW, ONRW, and TMDL screening completed

HIGH confidenceCRITICAL

All four screening checkboxes left unmarked on NOI page 3. The named receiving water tributary is within a 303(d)-impaired segment of the Stones River (pathogen impairment) per the 2024 303(d) list — applicant must affirmatively check 'impaired' and add the required BMP analysis.

CGP §3; Rule 0400-40-03noi-form.pdf· p. 3

Enhanced BMPs proposed for ETW/ONRW discharge

HIGH confidenceMAJOR

Receiving water is not classified as ETW or ONRW, so enhanced BMP requirements under §3.3 do not apply. Standard CGP BMPs are sufficient.

CGP §3.3noi-form.pdf· p. 3

SWPPP prepared, signed, and on file before discharge

HIGH confidenceCRITICAL

SWPPP prepared and signed by James Lin, P.E. (TN License #28391) on 2026-02-10. Certification box checked on NOI page 4.

CGP §5swppp.pdf· p. 1

SWPPP contains all required sections

HIGH confidenceCRITICAL

Six of seven required sections present and substantive: site description, pollutant sources, BMPs, stabilization schedule, inspection procedures, spill prevention. Missing: post-construction stormwater management section (§5.4.f). Required because the project will create > 1 acre of new impervious area.

CGP §5.4swppp.pdf· p. 14

Topographic site map attached

HIGH confidenceMAJOR

1"=50' topographic site map attached as site-map.pdf. Shows project boundary, disturbed area (4.3 ac), proposed drainage patterns, and two stormwater outfalls discharging to the unnamed Stones River tributary.

CGP §5.4.bsite-map.pdf· p. 1

Site acreage consistent across NOI, SWPPP, and site map

MEDIUM confidenceMAJOR

NOI: 4.2 ac · SWPPP §1: 4.5 ac · Site map measured: ~4.3 ac. Inconsistency of 0.3 ac may indicate an outdated SWPPP narrative or unclear boundary delineation.

CGP §2.1.d / §5.4Multiple

Outfall locations on NOI present in site map

HIGH confidenceMAJOR

NOI declares 2 outfalls. Site map shows 2 outfalls labeled OF-001 (NE corner) and OF-002 (SW corner) with coordinates matching the NOI values.

CGP §2.1.f / §5.4.bsite-map.pdf· p. 1